/ 6 December 2016

Eskom threatens fastest renewable expansion

Eskom's research
Eskom's research

Opposition from Eskom Holdings SOC Ltd. and government infighting threatens to sabotage the world’s fastest-growing green energy program.

Eskom is stalling on signing government-brokered deals to buy renewable energy from private producers, encouraged to develop capacity after outages over the past eight years hobbled the continent’s most industrialised nation. With the economy in the doldrums, the state utility says it no longer requires additional green power, arguing it’s not always available during peak demand periods and will push up prices for South African consumers.

Eskom’s reticence over renewables contrasts with its enthusiasm to find bidders for nuclear plants, even after the Energy Ministry last month proposed delaying new atomic reactors by 14 years. That contradiction reflects the schism at the heart of government, where President Jacob Zuma’s championing of nuclear power puts him at loggerheads with his Finance Minister Pravin Gordhan, who has questioned its affordability.

“There are strong political overtones to this,” said Professor Harald Winkler, director of University of Cape Town’s Energy Research Centre. “It doesn’t give investors in renewable energy consistency. It’s a way of exercising control by Eskom.”

Increasing Risk

Eskom has refused to sign off on an agreement to purchase 250 megawatts of power from two wind projects planned by Irish clean-energy developer Mainstream Renewable Power Ltd., and a deal with Saudi Arabia’s ACWA Power International to supply 100 megawatts of solar energy.

Eskom’s actions are “in contravention of government policy,” Mainstream Chief Executive Officer Eddie O’Connor said in a November 30 phone interview. “These guys have gone completely rogue. It’s increasing the risk of outside investors investing in South Africa fairly dramatically.”

Some projects haven’t been signed off because they are “very expensive,” Eskom spokesman Khulu Phasiwe said by phone.

“The price they are charging for their power is much higher than we are selling it for and higher than we are willing to pay,” he said. “The projects that came at a reasonable price, we were able to sign them on.”

Energy Minister Tina Joemat-Pettersson and Public Enterprises Minister Lynne Brown have done little to pull Eskom into line.

Since South Africa initiated its program to purchase renewable energy, independent producers have committed R194-billion ($14 billion) toward new infrastructure and as of June, 2,200 megawatts of power from 44 projects had been connected to the national grid. Asset finance for the projects rose fourfold last year, the most of any country in the world, Moody’s Investors Service said in a report.

Destroying Confidence

While Joemat-Pettersson has signed off on about 37 other projects worth R58-billion that will generate 2,354 megawatts of power and create about 4,800 construction jobs, developers are still waiting for Eskom to sign the off-take agreements.

“A program like this only works if you have got certainty and you’ve got continuity,” Wido Schnabel, head of business development for Africa at Canadian Solar, said by phone. “Now that the program has been stalled again because Eskom doesn’t want to sign the power-purchase agreements, it is destroying all the confidence and all the positives.”

Joematt-Pettersson told reporters on November 22 that determining South Africa’s optimal energy mix must take account of cost, security of supply, efficiency and the environment. Colin Cruywagen, a spokesman for Public Enterprises Minister Brown, who oversees Eskom, didn’t immediately respond to an e-mail seeking comment.

Too Expensive

In August, SMA Solar Technology AG cited the lack of commitment toward the green energy program as the reason for shutting its Cape Town factory and transferring production to China and Germany, where it has its headquarters.

Eskom can delay projects by letting quotes for connecting plants to the grid lapse, said Hein Reyneke, Mainstream’s business development manager for Africa. The quotes have been directed to the CEO’s office “but nothing comes out,” he said.

Eskom is building the Medupi and Kusile coal-fired plants that it estimates will cost at least R306-billion and will supply about 9,560 megawatts when both are complete. They have run over budget and are years behind schedule. Matshela Koko appointed Eskom’s acting CEO on December 1 has said the utility is shielding consumers from higher tariffs by not signing new off-take agreements.

“I understand where they are coming from,” said Robert Jeffrey, managing director and senior economist at Johannesburg-based advisory service Econometrix. “Eskom actually has a duty to supply efficient power at the lowest possible price. Clearly, renewables don’t allow it to do that at this stage of technological development.”

Monopoly Concerns

Winkler of the University of Cape Town disagrees, saying renewable energy prices, particularly for photovoltaics and wind, have come down dramatically.

“Those two are now cheaper than new coal or new nuclear,” said Winkler. “Any monopoly will have concerns about competition.”

South Africa only has an over-supply of electricity because of Eskom’s inability to previously meet demand halted new development and choked off growth, according to Schnabel of Canadian Solar. He sees energy storage solutions improving and decreasing in cost over the next five years, enabling renewable energy to be used at any time.

“We’re missing this huge opportunity,” he said. The developers take the risk and “all Eskom needs to say is that they’ll buy the energy from them over the next 20 years.”