Get more Mail & Guardian
Subscribe or Login

This is why we don’t have water

The department of water and sanitation is crippled. 

Where water should be flowing, it isn’t. Where sewage shouldn’t be flowing, it is. The leaps made to give people water after 1994 are being reversed, and some 20-million people no longer get regular clean water. This is despite enough dams and pipelines being built to get water to 95% of the population.

Most of this failure is the result of a cocktail of corruption, ineptitude and a shortage of engineering skills. Water projects are the biggest tenders available in provinces, with projects running into the millions or billions of rands, and they attract a lot of corruption. The department is running 15 projects each worth more than R1-billion, and 53 projects worth between R250-million and R1-billion.

Corruption accelerated during the tenure of former minister Nomvula Mokonyane. Irregular expenditure grew from a negligible R13-million in 2009 to R4-billion by the time she left in 2017 — almost a quarter of the department’s budget.

The department also maxed out its R2.6-billion overdraft facility with the Reserve Bank and had it frozen, while owing contractors more than R1.5-billion.

Little detail of what this all means was revealed by the department, beyond the new minister, Gugile Nkwinti, telling Parliament that he has inherited “a mess”. But this changed last month, when his department updated its parliamentary portfolio committee on the status of all its projects. What has emerged is a picture of dozens of projects delayed by a mix of corruption, angry residents, dubious contracts and general ineptitude on all sides.

The chairperson of the portfolio committee — the ANC’s Lulu Johnson — began by expressing “concern” because the department did not have a director general or a chief financial officer. “Countless” suspensions at the department had also taken place without the committee being told about them, he said.

Leonard Mannus, the department’s acting deputy director general, gave a Powerpoint presentation, digging into the failure of its projects. He explained how projects, from tiny to giant, were not working, and gave an idea of how they would be completed.

The most critical delays are in building new damsand raising the walls on old dams. In a semi-arid country that hasregular droughts, dams are crucial to allow peopleand industry to survive. It is dams that kept Cape Town going and that provide water to Gauteng, where there are no large rivers. Without dams, the next El Niño will mean cropfailure and people going thirsty.

In KwaZulu-Natal, R110-million has been budgeted to raise Hazelmere Dam’s wall. But because of a dispute,the contractor terminated the contract. Terminations mean the department has to pay penalty fees, and then to tender for a new contract. All this adds costs. A similar “contractual dispute” has delayed a R5-million dam for the Groot Marico area in North West, where crippling droughts regularly kill livestock and hammer farming. The dispute went unresolved and the contract expired before work could start.

In Ventersdorp, in the same province, a R16-million dam has been delayed because “top management” didn’t sign off on the appointment of an environmental control officer.

In Koffiefontein, in the Free State, a dam has been stopped by residents who are demanding that more local labour be used.

A budget of R209-million exists for raising the wall of Limpopo’s Tzaneen Dam. The department had to take the project over from Lepelle Northern Water,a subsidiary of the water department that has been mired in corruption, especially because of its failure to get water to people in Giyani.

A “loss of public confidence” and a number of cost overruns and contractual irregularities have resulted in the Tzaneen project being years behind schedule.

To solve these delays, the department said it has referred companies to the Special Investigating Unit (SIU) and other arms of government. The three companies involved in the Giyani project — LTE Consulting, Khato Civils and South Zambezi — are being chased by the unit for the R2.2-billion spent on that project. The SIU has asked that these 2014 contracts for the project be declared null and void.

Recovering misspent money is just one step that needs to be taken. The department must finish the projects. It told the parliamentary committee that the department’s building unit is now being used to complete work on many dams and pipelines.

In extreme cases, other solutions have been used. The R129-million Sebokeng wastewater treatment plant has been delayed by “constant community and labour unrest”, among other issues. The army has been deployed to stop the unrest and get the project completed.

That project appears to be moving along, and broken sewage plants are getting fixed. But other projects are still hamstrung by the R4-billion hole in the water department’s budget, and the nearly 1 000 unfilled jobs.

The parliamentary presentation did, at least, show the scale of the water crisis inS outh Africa.

Subscribe for R500/year

Thanks for enjoying the Mail & Guardian, we’re proud of our 36 year history, throughout which we have delivered to readers the most important, unbiased stories in South Africa. Good journalism costs, though, and right from our very first edition we’ve relied on reader subscriptions to protect our independence.

Digital subscribers get access to all of our award-winning journalism, including premium features, as well as exclusive events, newsletters, webinars and the cryptic crossword. Click here to find out how to join them and get a 57% discount in your first year.

Sipho Kings
Sipho Kings is the acting editor-in-chief of the Mail & Guardian

Related stories

WELCOME TO YOUR M&G

If you’re reading this, you clearly have great taste

If you haven’t already, you can subscribe to the Mail & Guardian for less than the cost of a cup of coffee a week, and get more great reads.

Already a subscriber? Sign in here

Advertising

Subscribers only

‘The children cannot cope any more’: Suicide in Calvinia highlights...

How Covid-19 has intensified the physical and emotional burdens placed on children’s shoulders.

Capitec Bank flies high above Viceroy’s arrow

The bank took a knock after being labelled a loan shark by the short seller, but this has not stymied its growth

More top stories

The convenient myth of an Africa spared from Covid-19

There are few, if any, studies to support Pfizer chief executive’s assertion that the global south would be more vaccine-hesitant than the north

Council wants Hawks, SIU probe into BAT’s Zimbabwe scandal

The cigarette maker has been accused of giving up to $500 000 in bribes and spying on competitors

How Alpha Condé overthrew Alpha Condé

Since the coup d’état, Guinea’s head of state has been in the custody of the military officers. But it was the president who was the primary architect of his own downfall
Advertising

press releases

Loading latest Press Releases…
×