Government delays nuclear plant plans as economy stagnates

South Africa delayed plans to build new nuclear power plants over concern about their cost and the waning demand for additional electricity as economic growth stalls.

Under a new timeline, the first nuclear power is expected to come on stream in 2037, with a total 20 385 megawatts of nuclear energy added to the national grid by 2050, according to the “base case” scenario outlined in a presentation about the department of energy’s updated Integrated Resources Plan. The proposal, released in Cape Town on Tuesday, also estimates as additional 37 400 MW of power from wind, 17 600 MW from solar plants, 35 292 MW from gas and 15 000 MW from coal by 2050.

The government previously said it wanted to generate 9 600 MW of energy from as many as eight reactors that should begin operating from 2023 and be completed by 2029. Price estimates had ranged from $37-billion to $100-billion. Although President Jacob Zuma has championed the nuclear programme, the treasury has cautioned that the country may be unable to afford new reactors at a time when the economy is barely growing and the budget deficit needs to be curbed to fend off a junk credit rating.

“Gas and renewables [will] form the biggest chunk of installed capacity by 2050,” the department of energy said in the presentation. “There is significant reduction in installed capacity from coal.”

The department, which has invited public comment on the proposals, also outlines two alternative scenarios that make different assumptions about costs, carbon emissions and the nation’s ability to generate additional renewable energy. One envisions 25 821 MW of nuclear power added to the grid between 2026 and 2049, and the other sees the production of 5 436 MW of new atomic power coming on line starting in 2037.


Power cuts
The energy plan will be refined in March next year and then submitted to Cabinet for final sign-off.

Eskom, the state-owned utility, has said it could use the more than R150-billion it will accumulate in reserves within 10 years to build new reactors. The utility operates Africa’s only nuclear power plant — the 1 800 MW Koeberg facility near Cape Town, which began operating in 1984.

Rosatom, Areva SA, EDF SA, Toshiba’s Westinghouse Electric unit, China Guangdong Nuclear Power Holding Corp and Korea Electric Power Corp previously expressed interest in building new reactors in South Africa.

South Africa experienced power cuts for about 100 days last year, as demand exceeded supply. Energy shortages eased as new generating capacity was bought on line, maintenance backlogs were addressed and a stagnating economy curbed power demand. – Bloomberg

Subscribe to the M&G

These are unprecedented times, and the role of media to tell and record the story of South Africa as it develops is more important than ever.

The Mail & Guardian is a proud news publisher with roots stretching back 35 years, and we’ve survived right from day one thanks to the support of readers who value fiercely independent journalism that is beholden to no-one. To help us continue for another 35 future years with the same proud values, please consider taking out a subscription.

Related stories

Advertising

Subscribers only

Ithala fails to act against board chairperson over PPE scandal

Morar asked to settle with the state and pay back the profit he made on an irregular tender

Vodacom swindled out of more than R24m worth of iPhones

A former employee allegedly ran an intricate scam to steal 8700 phones from the cellular giant

More top stories

Judicial Conduct Committee orders Mogoeng to apologise for his remarks...

The JCC said that by the chief justice straying into politics, he breached the judicial conduct code and ordered him to issue an apology and retraction

Millers pay for duty-free wheat quota

The South African Revenue Services didn’t gazette the EU quota rates for about month, with no reasons given – and then suddenly published them

Austerity budget unpacked

The finance minister has said it’s not an austerity project. But the numbers and economists disagree

Will job creation schemes fix the unemployment crisis?

Experts say there is no evidence yet to show that government-funded employment schemes work long term
Advertising

press releases

Loading latest Press Releases…