/ 17 September 2005

A massive clean-up after a massive hurricane

In a sandy construction site on the outskirts of town, more than a dozen trucks wait for their chance to unload tree limbs and feed a huge bonfire that will burn from dawn until dusk every day for months.

In an abandoned tanning salon a few towns away, members of the Army Corps of Engineers kneel on the floor and look for available dump sites on maps laid on the carpet.

The Hurricane Katrina clean-up represents the biggest waste-disposal job in United States history, dwarfing in volume the debris carted off after the World Trade Centre’s twin towers fell in 2001, officials said.

In the past few days, a loose network of contractors, government officials and out-of-work residents has sprung up to scoop, sort, grind and dispose of the mountains of garbage produced when entire communities were reduced to rubble.

Engineers and environmental officials are scrambling to figure out where to put the debris. The largest dump site in south-eastern Mississippi is already nearing capacity.

Zogas Costas, the army-corps engineer leading the clean-up in two south-eastern Mississippi counties, said aerial photos suggest Mississippi has as much as 38-million cubic metres of debris — enough to fill Atlanta’s Georgia Dome nearly 13 times.

Louisiana, where thousands upon thousands of flooded-out homes in and around New Orleans will probably have to be razed, could have nearly as much.

”I was at 9/11. That was done in about four months,” Costas said. ”This is going take longer.”

The clean-up in Mississippi follows a process that will probably be adopted in Louisiana as well.

First, construction crews use bulldozers and backhoes to load trucks with debris and haul it to ”reduction sites”. There, most household debris — mattresses, vinyl siding, toys, rusted metal, lumber and the likes — is separated out and ground up together.

Trees, shrubs and brush are either burned or turned into wood chips.

Air conditioners, refrigerators and other items that could contain hazardous materials such as coolant are set aside. The dangerous substances will be removed before the items are ground up, too.

Officials hope to recycle the wood chips for landscaping or road building. The ground-up plastic and metal will be sent to landfills.

To handle the load, Mississippi will need dozens of new landfills and reduction sites amounting to hundreds of hectares, said Mark Williams, a programme manager with the state department of environmental quality.

Some closed sites may be reopened, existing landfills may be expanded and people with land to spare have called the state, looking to get in on the action.

”Land is going to be at a premium,” Costas said. ”It’s a huge, enormous task.”

Approving such a site normally takes months, but environmental officials have speeded up the process.

Senator James Inhofe, a Republican from Oklahoma, has been preparing a Bill that will allow the Environmental Protection Agency to waive certain environmental rules during the clean-up, though agency administrator Stephen Johnson said there is no immediate need for such waivers.

As for how long the clean-up could last, Costas said much of the debris will be removed from the streets within three months. But burning and grinding it all could take years. — Sapa-AP