Eskom’s Medupi and Kusile to cost R36bn to complete, will not be halted — Mabuza

Construction on the Medupi and Kusile power stations will go ahead as the cost of halting the projects will not benefit the economy, the Chairperson of the Eskom board Jabu Mabuza has said.

The power plants are expected to cost R18-billion each.

Mabuza was speaking at a media briefing on the state of South Africa’s power supply on Wednesday along with other Eskom executives and Public Enterprises Minister Pravin Gordhan.

The building of the coal-fired power stations, which started in 2007 and 2008, has been hit by cost overruns, poor engineering designs and allegations of corruption.

Mabuza said questions had been raised on whether it would be feasible to stop construction on the multi-billion rand coal plants now or to continue the process until completion.

READ MORE: Medupi and Kusile: Costly and faulty

“We have done the exercise and have concluded that the costs of not continuing is not going to be met by the benefit of continuing,” said Mabuza.

He said the questions about the viability of stopping the construction at the two mega power plants had been raised by some board members who wanted to know the cost implications if the projects were to be stopped.

“Given that they are at a point where they are almost complete… it would cost around R18-billion each to complete,” he said.

Mabuza said that should they not complete the projects, it was estimated that an additional cost of more or less R8-billion would be incurred in contractual, legal costs and penalties.

“So if you stop this, then you are going to have to build something else.”

He said this could take between 60 and 66 months.

Once hailed as the answer to the country’s electricity supply challenges, the costs for the plants have already escalated to over R300-billion, as revealed this year by the Department of Public Enterprises before a parliamentary Portfolio Committee.

Once completed, Medupi power station was expected to consist of six units, with an installed capacity of 4 764MW. In October 2018, Eskom announced that five of its six units had been synchronised to the national power grid

Unit 1 of Kusile went live in August 2017, according to the power utility. The facility will have six units, each producing 800MW of electricity.

Sunday Times report this year revealed that the Special Investigating Unit (SIU) was investigating alleged theft of R139-billion related to the construction of Medupi and Kusile power stations.

According to the newspaper, the SIU is looking at 11 contractors as part of its investigation into the building of the two facilities. — Fin24

We make it make sense

If this story helped you navigate your world, subscribe to the M&G today for just R30 for the first three months

Subscribers get access to all our best journalism, subscriber-only newsletters, events and a weekly cryptic crossword.”

Related stories

WELCOME TO YOUR M&G

Already a subscriber? Sign in here

Advertising

Latest stories

Covid-19 escalates xenophobia in South Africa – Report

Politicians have increasingly come under scrutiny for their alleged inflammatory comments which have been taken as endorsement by anti-foreigner activists

Metaverse: Virtual economy to pump $40bn into African GDP

A study suggests that the virtual world platform could plug more than 40 billion US dollars into the African economy in its first decade.

Bradley Carnell’s shot at US footballing greatness

St Louis City’s head coach has the opportunity to build a legacy from scratch at the midwest club, the latest franchise added to the Major League Soccer.

How to safeguard your digital footprint in cyberspace

Apply physical security measures in cyberspace; if you won’t open your door to a stranger, why accept offers and requests from strangers online?
Advertising

press releases

Loading latest Press Releases…
×