Eskom’s Medupi and Kusile to cost R36bn to complete, will not be halted — Mabuza

Construction on the Medupi and Kusile power stations will go ahead as the cost of halting the projects will not benefit the economy, the Chairperson of the Eskom board Jabu Mabuza has said.

The power plants are expected to cost R18-billion each.

Mabuza was speaking at a media briefing on the state of South Africa’s power supply on Wednesday along with other Eskom executives and Public Enterprises Minister Pravin Gordhan.

The building of the coal-fired power stations, which started in 2007 and 2008, has been hit by cost overruns, poor engineering designs and allegations of corruption.

Mabuza said questions had been raised on whether it would be feasible to stop construction on the multi-billion rand coal plants now or to continue the process until completion.

READ MORE: Medupi and Kusile: Costly and faulty

“We have done the exercise and have concluded that the costs of not continuing is not going to be met by the benefit of continuing,” said Mabuza.

He said the questions about the viability of stopping the construction at the two mega power plants had been raised by some board members who wanted to know the cost implications if the projects were to be stopped.

“Given that they are at a point where they are almost complete… it would cost around R18-billion each to complete,” he said.

Mabuza said that should they not complete the projects, it was estimated that an additional cost of more or less R8-billion would be incurred in contractual, legal costs and penalties.

“So if you stop this, then you are going to have to build something else.”

He said this could take between 60 and 66 months.

Once hailed as the answer to the country’s electricity supply challenges, the costs for the plants have already escalated to over R300-billion, as revealed this year by the Department of Public Enterprises before a parliamentary Portfolio Committee.

Once completed, Medupi power station was expected to consist of six units, with an installed capacity of 4 764MW. In October 2018, Eskom announced that five of its six units had been synchronised to the national power grid

Unit 1 of Kusile went live in August 2017, according to the power utility. The facility will have six units, each producing 800MW of electricity.

Sunday Times report this year revealed that the Special Investigating Unit (SIU) was investigating alleged theft of R139-billion related to the construction of Medupi and Kusile power stations.

According to the newspaper, the SIU is looking at 11 contractors as part of its investigation into the building of the two facilities. — Fin24

Subscribe for R500/year

Thanks for enjoying the Mail & Guardian, we’re proud of our 36 year history, throughout which we have delivered to readers the most important, unbiased stories in South Africa. Good journalism costs, though, and right from our very first edition we’ve relied on reader subscriptions to protect our independence.

Digital subscribers get access to all of our award-winning journalism, including premium features, as well as exclusive events, newsletters, webinars and the cryptic crossword. Click here to find out how to join them and get a 57% discount in your first year.

Related stories

WELCOME TO YOUR M&G

If you’re reading this, you clearly have great taste

If you haven’t already, you can subscribe to the Mail & Guardian for less than the cost of a cup of coffee a week, and get more great reads.

Already a subscriber? Sign in here

Advertising

Subscribers only

Basic web lessons for South Africa: Government hacks point to...

Recent cyberattacks at the department of justice and the space agency highlight the extent of our naïveté

‘The children cannot cope any more’: Suicide in Calvinia highlights...

How Covid-19 has intensified the physical and emotional burdens placed on children’s shoulders.

More top stories

Sisters pave the way with ecobricks

The durable bricks are made from 30% recycled plastic, some of which they collect from a network of 50 waste pickers

If the inflation-driving supply strain in the US lasts, it...

In South Africa, a strong trade surplus, buoyed by robust commodity prices, will cushion our economy against pressure arising from US policy

Farmers squeezed by big retailers

It may be beneficial for consumers when supermarkets push to get the lowest price from suppliers, but it can harm the farmers

Covid-19: No vaccine booster shots needed yet

Scientists agree it is important to get most of the population vaccinated before giving booster jabs
Advertising

press releases

Loading latest Press Releases…
×