Eskom’s Medupi and Kusile to cost R36bn to complete, will not be halted — Mabuza

Construction on the Medupi and Kusile power stations will go ahead as the cost of halting the projects will not benefit the economy, the Chairperson of the Eskom board Jabu Mabuza has said.

The power plants are expected to cost R18-billion each.

Mabuza was speaking at a media briefing on the state of South Africa’s power supply on Wednesday along with other Eskom executives and Public Enterprises Minister Pravin Gordhan.

The building of the coal-fired power stations, which started in 2007 and 2008, has been hit by cost overruns, poor engineering designs and allegations of corruption.

Mabuza said questions had been raised on whether it would be feasible to stop construction on the multi-billion rand coal plants now or to continue the process until completion.

READ MORE: Medupi and Kusile: Costly and faulty

“We have done the exercise and have concluded that the costs of not continuing is not going to be met by the benefit of continuing,” said Mabuza.

He said the questions about the viability of stopping the construction at the two mega power plants had been raised by some board members who wanted to know the cost implications if the projects were to be stopped.

“Given that they are at a point where they are almost complete… it would cost around R18-billion each to complete,” he said.

Mabuza said that should they not complete the projects, it was estimated that an additional cost of more or less R8-billion would be incurred in contractual, legal costs and penalties.

“So if you stop this, then you are going to have to build something else.”

He said this could take between 60 and 66 months.

Once hailed as the answer to the country’s electricity supply challenges, the costs for the plants have already escalated to over R300-billion, as revealed this year by the Department of Public Enterprises before a parliamentary Portfolio Committee.

Once completed, Medupi power station was expected to consist of six units, with an installed capacity of 4 764MW. In October 2018, Eskom announced that five of its six units had been synchronised to the national power grid

Unit 1 of Kusile went live in August 2017, according to the power utility. The facility will have six units, each producing 800MW of electricity.

Sunday Times report this year revealed that the Special Investigating Unit (SIU) was investigating alleged theft of R139-billion related to the construction of Medupi and Kusile power stations.

According to the newspaper, the SIU is looking at 11 contractors as part of its investigation into the building of the two facilities. — Fin24

PW Botha wagged his finger and banned us in 1988 but we stood firm. We built a reputation for fearless journalism, then, and now. Through these last 35 years, the Mail & Guardian has always been on the right side of history.

These days, we are on the trail of the merry band of corporates and politicians robbing South Africa of its own potential.

To help us ensure another 35 future years of fiercely independent journalism, please subscribe.

Advertisting

South Africa has been junked

Treasury says the credit ratings downgrade “could not have come at a worse time”, as country enters a 21-day Covid-19 lockdown with little money saved up

Mail & Guardian needs your help

Our job is to help give you the information we all need to participate in building this country, while holding those in power to account. But now the power to help us keep doing that is in your hands

Press Releases

The online value of executive education in a Covid-19 world

Executive education courses further develop the skills of leaders in the workplace

Sisa Ntshona urges everyone to stay home, and consider travelling later

Sisa Ntshona has urged everyone to limit their movements in line with government’s request

SAB Zenzele’s special AGM postponed until further notice

An arrangement has been announced for shareholders and retailers to receive a 77.5% cash payout

20th Edition of the National Teaching Awards

Teachers are seldom recognised but they are indispensable to the country's education system

Awards affirm the vital work that teachers do

Government is committed to empowering South Africa’s teachers with skills, knowledge and techniques for a changing world

SAB Zenzele special AGM rescheduled to March 25 2020

New voting arrangements are being made to safeguard the health of shareholders

Dimension Data launches Saturday School in PE

The Gauteng Saturday School has produced a number of success stories