Get more Mail & Guardian
Subscribe or Login

Medupi power station’s completion delayed

It was announced on Monday at a press conference that the first unit of the Medupi station will only come online by the middle of next year, putting the project six months to a year behind schedule. The press conference was addressed, by among others, Eskom chief executive Brian Dames.

Until a few months ago Public Enterprises Minister Malusi Gigaba said the December 2013 deadline for the long awaited power station still stood.

The site was temporarily closed in January when workers went on strike increasing fears that this power station would be delayed. 

The six different generating units, the boilers, are expected to generate about 800MW of electricity each. Boiler six was expected to deliver electricity to the grid at the end of 2013, which will obviously now not happen. 

In April, Gigaba warned that service providers would face tough penalties if the Medupi power station did not meet its December 2013 deadline.

"I wish to make it unequivocally clear that I will not tolerate any delays to the delivery of this unit," said Gigaba.

Load shedding
Later in April, analysts and people working in the industry said they believed load shedding to be a very real possibility, given that our electricity system is running with almost no reserves.

In a quarterly state-of-the-system briefing, given in Johannesburg and then again in Parliament at the time, Eskom revealed just how tight things have become for the country.

The week began on a reserve margin of 881MW – or just under 3%. This almost non-existent breathing room for the country's power system has become a common occurrence in recent months. On April 22, a unit at Koeberg was returned to service, adding 900MW to the grid.

The power line that transports electricity from Cahora Bassa in Mozambique to South Africa is expected to be back up and running by the end of April, adding another 600MW. The 1 500MW supply from Cahora Bassa has been patchy since the middle of last year after a technical failure at a substation in Mozambique.

This was followed by the transmission line going down due to floods in January. To cope with these supply problems Eskom has, for some months, been holding off on the maintenance it normally does in summer and has run its diesel-fuelled peaking power plants at the highest rates seen in the past four years to keep the lights on.

But Dames made it clear that it can no longer defer this maintenance because a number of power stations have reached their technical limits and the longer maintenance is put off the more unreliable plants become, and the greater the risk of unplanned outages.

"Necessary penalties will be at hand should any delays be experienced. Heads will roll." Given the current power system constraints it was critical for Medupi to be completed on time, he told reporters after inspecting the Medupi construction site in Lephalale with senior officials and Eskom chief executive Brian Dames.

Gigaba said South Africa did not have the "luxury of time to brook any delays".

Delays
?Additional measures were put in place to improve productivity at Medupi, including seven-day work weeks, two shifts a day, and additional senior project management and technical staff.

"There is recognition that the delays and additional measures being put in place to recover lost time may result in costs overruns which Eskom will resolve through remedies provided for in the contracts," he said.

?In January, Eskom temporarily closed the power station when contract workers went on strike. Gigaba said this closure was the longest at the site – more than 10 weeks. Dames said construction at Medupi was on a "tight schedule".

"As Eskom, we will do whatever it takes to ensure that we deliver by its target," he told reporters.

When Medupi's timelines were reviewed in November 2012 it was found the target date of first power by late 2013 could be achieved with "significant effort". – Additional reporting by Sapa

Subscribe to the M&G

Thanks for enjoying the Mail & Guardian, we’re proud of our 36 year history, throughout which we have delivered to readers the most important, unbiased stories in South Africa. Good journalism costs, though, and right from our very first edition we’ve relied on reader subscriptions to protect our independence.

Digital subscribers get access to all of our award-winning journalism, including premium features, as well as exclusive events, newsletters, webinars and the cryptic crossword. Click here to find out how to join them and receive a 40% discount on our annual rate..

Related stories

Advertising

Subscribers only

Q&A Sessions: Zanele Mbuyisa — For the love of people-centred...

She’s worked on one of the biggest class-action cases in South Africa and she’s taken on Uber: Zanele Mbuyisa speaks to Athandiwe Saba about advocating for the underrepresented, getting ‘old’ and transformation in the law fraternity

Update: Standard Bank rejects climate proposal

Climate considerations are pressing Standard Bank shareholders to push for the recusal of those with fossil fuel ties.

More top stories

Denel money woes clip air force’s wings

A senior officer says the shortage of spares and and ability to service aircraft and vehicles has a negative effect on the SANDF’s operational ability

State fails at-risk children as R55m orphanage stands empty

Boikagong Centre in Mahikeng has been closed for almost two years because it did not meet safety requirements. The discarded children say they want a safe place to learn, but instead endure rape and other violence

Wildlife farming vs Creecy’s panel

The departments of environment and agriculture legislation are at odds over modifying the genes of wild animals

Drugs and alcohol abuse rage in crime stats

Substance abuse has emerged as a reason for the spike in crimes during the first quarter of 2021.
Advertising

press releases

Loading latest Press Releases…
×